EMS-Trade
Cooling
Loop consumables

Document ECT-01 · REV C · ISSUED 2026-09 Six lines · 48 sheets

Line 06 · fill and flush · sheet 3 of 3

Commissioning is run by the installing contractor. We supply what it consumes.

The step has three figures written into it: the target the flush has to reach, the point the sample is drawn from, and the rule that says the loop may be charged. Those three are set out below as conditions. The fluid, the elements, the valves and the instruments that read them are the part we ship.

Request the specification file Consumable list, written against your target
A loop manifold before charge with the flush hoses still connected, a sampling valve open at the return, and the drums and element boxes staged against the wall behind
FIG 01 ·

The hour before the charge. Everything on this sheet is either in this frame or has just been taken out of it.

01

The three figures the step is held to, and the envelope around them

Schedule A · target, sampling point, acceptance

Commissioning · every row is a condition that can be checked on the day, or past its edge
No Condition Value Unit Past the edge
01 Flush target before charge ISO 4406 17/15/12 three classes The owner may write a stricter figure. Then the schedule runs to the owner's number and ours is the floor, not the target
02 Sampling point on the return return leg upstream of charge Drawn from the tank instead, the sample describes the fluid that has not been round the loop yet, and it reads clean earlier than the loop is
03 Acceptance the rule all three classes same sample Met at one sampling, not averaged across two. A loop that passes on the second draw has not passed
04 Flush fluid what is put through 0.05 – 100 µm element ladder The two elements the fluid passes on its way round are drawn from the eight-step absolute ladder; 20 in and 40 in in the standard housings, 10 in on a small branch
05 Element change the stop rule 0.5 – 0.7 bar Across the housing. Past it the element is bypassing and the loop is being circulated rather than filtered
06 Water quality read beside the sample µS/cm · pH two readings Particle count says whether the loop is clean; conductivity and pH say whether what is left in it will stay inert once the coolant is in
07 Loop side the hardware it meets 1.38 MPa working Hose and couplings in the same range as the rest of the loop, burst above 5.5 MPa, coolant quoted −40 ~ +99 °C
A sample drawn at a return line into a clear bottle held against the light, the fluid faintly hazy against the background behind it
FIG 02 ·

The sample is the only evidence that matters. Everything else on this sheet is arranged to make that one bottle mean something.

A differential gauge fitted across a filter housing on a flush rig, its needle off the zero stop, with the two impulse tubes looped above it
FIG 03 ·

The stop rule, read where it is decided. A climb from the clean-water zero is the only signal that the element is done.

02

Three ways the step is failed, and what each one looks like

Failure modes · photographed on the article, not drawn

None of these three shows up as a leak. All three are found later, as a conductivity that will not settle, a pump that has to work harder, or a filter that loads in a month instead of a year.

Two sample bottles side by side on a bench: the left one cloudy with suspended solids against the light, the right one clear
FIG 04 ·

Charged early. The flush was stopped while the sample still carried solids, and they went into the coolant instead of the element.

A loaded element lifted out of its housing with the pleats packed solid on the outer face and the inner face still clean, the differential gauge behind it
FIG 05 ·

Run past the stop rule. The first stage packed up, flow went round it, and the flush carried on looking normal.

The inside of a drained hose run with a pale ring of dried solids left along the low side of the bore, caught by a light from the open end
FIG 06 ·

Not drained. What dries in the low side of a run re-dissolves into the charge, and the conductivity moves from the first day.

Checkable before the charge is opened · sample clarity against the light · differential from the clean-water zero · drain point at the low end · conductivity and pH beside the particle count · the element record against the hours run

03

What the step puts through, against what it meets

Schedule B · medium against material, one judgement per cell

Compatibility · the medium in the bore against the four materials the commissioning step reaches
Medium EPDM seal EPDM hose 304 / 316L Brass valve
Flush water, deionised
Glycol mix, up to 20%
The charge itself
Flush fluid residue
Coolant above +99 °C
Air side, ozone and UV

Tick within the quoted envelopeDash needs the inhibitor package checked firstCross outside the quoted envelope

Nine green elastomer O-rings arranged on a white ground, all the same section, photographed from above with one soft shadow across the group
FIG 07 ·

Seals as they arrive. The colour is a compound code, and the compound is what the matrix above is written about.

Five black elastomer O-rings on a white ground in a loose arrangement, their sections round and unmarked
FIG 08 ·

The black compound, EPDM, and the one that carries most of the joints on a flushed loop.

04

Where each consumable sits once the loop is real

Installation form · four positions the step uses

Four places on a real installation decide whether the figures in Schedule A can be met at all: where the flush enters, where the sample is drawn, where the loop drains, and where the instrument is read. All four are marked on the outline drawing that goes with the order.

The step itself is carried out by the installing contractor, on the contractor's programme. What is settled here is the hardware, so that the four positions exist before anybody needs them.

A flush rig connected to the lowest point of a loop in a plant room, its hose crossing the floor with a drip tray under the connection and the drum beside it
FIG 09 ·

Entry and drain. Low point out, high point in, and a tray under the connection nobody planned for.

A sampling valve welded on a return line above a drip tray, its outlet capped and the pipe insulation cut back around the boss
FIG 10 ·

The tap, on the return. Fitted while the pipe was open, not added the day the sample was wanted.

A flush hose dressed along a cable tray with clamps at intervals, the run turning down to a manifold end without a low point in it
FIG 11 ·

A hose run with no low point in it. Every dip in the run is a place the flush water stays after the drain.

Instruments mounted on a board beside a loop: a particle counter, a conductivity transmitter and a pH transmitter, their faces angled out with no numbers legible
FIG 12 ·

Read where the sample is taken. Conductivity and pH are taken beside the particle count, not days later from a different point in the loop.

05

What ships with the consumables

Documents · written for the step, not for the file

Consumable list
the items the step needs, against the target written on the order
Outline drawing
the four positions: fill, sample, drain, instrument
Element record
rating and batch of every element supplied, with the 0.5 – 0.7 bar change figure restated
Material certificate
wetted metal to EN 10204 3.1
Sampling schedule
the point, the classes and the acceptance rule, on one page
Packing and lead time
crate to ISPM 15, sampling 7–10 days, production 25–35 days
A document packet on a bench next to a coiled flush hose: a folded outline drawing, a stapled sampling schedule and a certificate sheet, blank of print
FIG 13 ·

One page of the pack is the one that gets carried up the ladder, and it is the outline drawing.

Elements in their sleeves standing in a row against a crate, each sleeve marked with a blank tag and the ratings ordered coarse to fine
FIG 14 ·

Supplied in order, coarse to fine, so the first stage and the second cannot be swapped by accident on site.

On this line · Fill and flush · Fill and flush carts · Water quality · Fluid quality monitoring

DOCUMENT REQUEST

Request the consumable list

The consumable list, the sampling schedule, the outline drawing and the material certificate. Tick what you need.

If the form cannot send, this address takes the request instead: sales@ems-cool.com
The only promise on this page

One business day, with the file attached.

Nothing else on this sheet is promised. Price, stock and lead time are quoted against a request.

An element in its sleeve held upright on a bench with the sleeve open at the top and the pleats visible inside
PL 01 ·

One sleeve, one rating. The two stages are supplied apart because on site they are fitted in one order.

A clean sample bottle standing on a bench beside its cap and a spare, all unlabelled and dry, with a rack of them behind out of focus
PL 02 ·

Bottles are supplied clean and dry. A bottle rinsed in tap water is a sample that reports the tap.